LEWALLEN BRIDGE REPLACEMENT PROJECT UPDATE

Lynn Murphy (Project Coordinator)At month 26 of the 36-month project:Crews continue preparing the bridge deck for concrete:Bridge Deck DrainsDrains spaced at engineered intervals are being installed where the drain gutter meets the concrete curb/sidewalk. This is time consuming work, as the recently installed deck rebar steel must be trimmed away …

Read More »

Lane Closures on Green Bridge for construction

Construction crews blasted today at the site of the new bridge that will place the Lewallen Bridge in 2020. Today (Monday, January 7th) between 12:00 and 1:00 p.m., Clinch Avenue was closed between Carden Farm Drive and South Seivers Blvd. for about 5 minutes while some blasting takes place on …